Metrics
tidanote computes four things automatically. You never fill in a status report — the numbers come from the tasks in your notes.
Progress (0–100%)
Section titled “Progress (0–100%)”How much of the project is done.
- Each task counts: done = 1, doing = 0.5, open = 0.
- Averaged across the project’s tasks and its sub-projects (recursively).
- No tasks and no sub-projects → 0%.
Example: two tasks, one done and one doing → (1 + 0.5) / 2 = 75%.
Schedule — On track / Ahead / Behind
Section titled “Schedule — On track / Ahead / Behind”Whether you’re keeping pace with the target date.
- Compares % complete against % of the time elapsed (from start/created to the target date).
- Tolerance is ±10%.
- Only shown when a target date is set and the project isn’t done.
Example: 50% of the time has passed but only 20% is done → Behind.
Velocity
Section titled “Velocity”How fast tasks are being completed.
- = tasks completed ÷ days, over the last 14 days.
Example: 7 tasks completed in the last 14 days → 0.5 per day.
Scope change
Section titled “Scope change”Whether the project is growing or shrinking — this is the “churn” number.
- = tasks added − tasks removed, over the last 14 days.
- Positive = scope grew (creep). Negative = scope was cut.
Example: +3 means three more tasks were added than removed in the last 14 days.
Pulse driver — “why is this late”
Section titled “Pulse driver — “why is this late””Only appears when a project is past its target date and not done. It names the most likely cause:
- Slow velocity — few tasks completed.
- Scope creep — more tasks added than completed.
- Schedule slip — the target date was too aggressive.
The scope-events log
Section titled “The scope-events log”These numbers come from an automatic log of every task change:
task_added,task_removed,task_completed,task_reopeneddue_changed,priority_changed,assignee_changed
Done ≠ removed. Ticking a task is progress; deleting an open task is scope reduction; deleting an already-done task is just cleanup — so it isn’t counted as churn.